1. PRINCIPAL ACCOUNTABILITIES:
Accountabilities Major Activities Quality Management
1. Quality Planning & Documentation
* Implement Field Quality Plan (FQP) and Inspection & Test Plans (ITPs) for
substation and Transmission line works.
* Prepare, Review and approve contractors’ method statements and work
procedures.
* Prepare & Implement PQP, SOP, Check lists & Formats in line with TS, Codes &
Standards and FQP.
* Maintain comprehensive QA/QC records — inspection reports, RFI’s, Check
Lists, RA Bills, FOM & NCR’s, calibration certificates, test results, and
approvals.
* Verification of material and equipment quality against approved drawings and
specifications.
* Check manufacturer’s test certificates and shipping documents.
* Site inspection for:
* Transformers, Reactors, GIS/AIS equipment, breakers, CTs, PTs, isolators,
LA, SVG’s, HT/LT SGR Panels .
* Conductors, insulators, hardware fittings.
* Steel structures, tower members, bolts/nuts, earthing materials.
1. Stores Management
* Auditing & Inspecting Stores
* Audit Report Generation & ensure compliance on findings
* Ensure to follow Stores SOP & OEM Guidelines in storing and preservation.
2. Incoming Material Inspection
1.
4. Substation Installation Quality Oversight
* Civil works: Excavation, PCC, RCC foundations, trenches, cable ducts, Back
Filling, Roads, control room building as per specs.
* Cubes Casting , Traceability, Curing & Testing.
* Electrical/mechanical works: erection of gantries, busbars, GIS bays,
switchgear, transformers, SGR Panels and auxiliary systems.
* Torquing & Marking.
* Cable laying, Crimping, termination, glanding, and control panel wiring.
* Witness functional and electrical tests: Ratio, Magnetic Balance, Vector
group, Winding Resistance, Oil DGA, BDV, SFRA, Insulation resistance,
contact resistance, ratio tests, SF6 Breaker timing, gas leakage, relay
testing.
* Tower foundation type checks (pile, raft, chimney, pad & chimney, etc.).
* Cubes Casting , Traceability, Curing & T