- Read approved SLDs, cable schedules, termination drawings, panel schematics and manufacturer instructions.
- Identify cable size, core, voltage grade, gland type, lug size, entry method and termination point before starting.
- Perform cable measurement, cutting, sheath removal, armour preparation, gland installation, ferruling, lug crimping, heat-shrink application, dressing and phase identification without damaging insulation or strands.
- Use the correct calibrated crimping die and complete bolted connections using the approved torque value and calibrated torque wrench.
- Install light fixtures, junction boxes, conduits/trunking, flexible conduit, supports, switches, sockets, local isolators and earthing/bonding connections.
- Perform continuity, insulation resistance and polarity checks only under an approved test method and supervision; record results.
- Maintain bend radius, segregation, support, tagging, gland sealing, IP protection,
housekeeping and clean-work controls.
- Report drawing mismatch, damaged cable/equipment, incorrect material, unsafe condition or failed test immediately. Do not improvise unauthorized joints or modifications.
Acceptance / skill-test criteria
- Correctly selects gland, lug and die for sample cable; explains cable construction and termination sequence.
- Produces a sample termination with undamaged conductor, complete crimp, correct gland assembly, phase marking, neat dressing and verified torque.
- Demonstrates protected use of hydraulic crimper, stripper/knife, multimeter, insulation tester and torque wrench.
- Demonstrates lighting circuit installation and basic fault identification without bypassing protective devices.