Read approved SLDs, cable schedules, termination drawings, panel schematics and manufacturer instructions.
Identify cable size, core, voltage grade, gland type, lug size, entry method and termination point before starting.
Perform cable measurement, cutting, sheath removal, armour preparation, gland installation, ferruling, lug crimping, heat-shrink application, dressing and phase identification without damaging insulation or strands.
Use the correct calibrated crimping die and complete bolted connections using the approved torque value and calibrated torque wrench.
Install light fixtures, junction boxes, conduits/trunking, versatile conduit, supports, switches, sockets, local isolators and earthing/bonding connections.
Perform continuity, insulation resistance and polarity checks only under an approved test method and supervision; record results.
Maintain bend radius, segregation, support, tagging, gland sealing, IP protection,
housekeeping and clean-work controls.
Report drawing mismatch, damaged cable/equipment, incorrect material, unsafe condition or failed test immediately. Do not improvise unauthorized joints or modifications.
Acceptance / skill-test criteria
Correctly selects gland, lug and die for sample cable; explains cable construction and termination sequence.
Produces a sample termination with undamaged conductor, complete crimp, correct gland assembly, phase marking, neat dressing and verified torque.
Demonstrates protected use of hydraulic crimper, stripper/knife, multimeter, insulation tester and torque wrench.
Demonstrates lighting circuit installation and basic fault identification without bypassing protective devices.